I began a project back in Nov. which was to conclude appx. mid Dec. The project was in 2 phases. The fee schedule was set up for three payments. 1/3 to start, 1/3 at end of phase 1, and 1/3 at end of phase 2. Midway through ph2 they hire a new project manager who decides to put the project on hold while he rethinks their strategy. FINALCHECKUS INTERRUPTUS! Met with them yesterday and they're all ready to continue ph2, but with modifications to the original plan. WTF?
This is 20 days beyond the planned completion date with no loot from them until and of Jan. I think I should negotiate a new contract but (obviously) I am unsure.
Thoughts?
Sorry for the long post.
Thanx!
- jox0
I don't even understand how you can be hesistant to negotiate your contract here.
It was based on a timetable that has changed. Just do it.
- robotron3k0
the industry term you're referring to is called, "scope creep" and for that you should tell you're client you will be happy to do a "change order" for them.
- OSFA0
agree. go get 'em tiger!
- k0na_an0k0
agree. renegotiate.
- _salisae_0
agree. renegotiate.
k0na_an0k
(Jan 5 07, 13:21)hahhahhahhhahaha!
- johndiggity0
def warrants a change order and possibly an agreement on a revised schedule/estimate.
- ItTango0
*looks in mirror. sniffs arm pits and flexes muscles*
OK. Renegotiate it is.
Thanx for the feedback!Robo: is "scope creep" really the term?
- design_naked0
DEFINITELY new contract. NO QUESTION. I've run into this before. It is outside the scope of the original contract so you must write up a new one with different (additional) monies as they are asking you to do more now.
- k0na_an0k0
agree. renegotiate.
k0na_an0k
(Jan 5 07, 13:21)hahhahhahhhahaha!
_salisae_
(Jan 5 07, 13:24)is there a reason you're laughing after everything i say? you mockin me?
- jox0
is there a reason you're laughing after everything i say? you mockin me?
k0na_an0k
(Jan 5 07, 13:29)pfft. women. *rolls eyes
- OSFA0
agree. renegotiate.
k0na_an0k
(Jan 5 07, 13:21)
hahhahhahhhahaha!
_salisae_
(Jan 5 07, 13:24)is there a reason you're laughing after everything i say? you mockin me?
k0na_an0k
(Jan 5 07, 13:29)MEOW!!! rrrgghhhh.
- jox0
Careful. Don't anger it.
- ItTango0
Again, thanx all. Anybody doing any straight hourly billing?
- OSFA0
well, flavorful usually charges per session...
;)
- design_naked0
Again, thanx all. Anybody doing any straight hourly billing?
ItTango
(Jan 5 07, 13:35)Nope, only gay hourly billing.
- jox0
If you negotiate a fixed price for something, always set an hourly rate as well in the contract for any additional time, and for situations like these.
- ItTango0
Nope, only gay hourly billing.
design_naked:D
- ItTango0
If you negotiate a fixed price for something, always set an hourly rate as well in the contract for any additional time, and for situations like these.
jox
(Jan 5 07, 13:41)Yes... Silly me.
- robotron3k0
scope creep isn't really a term you might say to a client but it's basically what clients tend to do, try and squeeze in work outside of the statment of work (SOW). and feel free to use acronyms like that infront of the client, so things sound more legal.